Table of Contents
ToggleProject Background:
Coolnet has deployed a cutting-edge data center in Singapore to support the rising demand for hyperscale cloud services and mission-critical digital infrastructure in Southeast Asia. Designed to meet Tier III+ standards, the facility prioritizes energy efficiency, scalability, and resilience, aligning with Singapore’s Green Data Center Roadmap.
Project Configuration:
1. Main Equipment Room
Micro-Modules: 4 double-row micro-modules, each housing:
20 server cabinets (80 cabinets total).
5 × 70kW CyberMaster series precision air conditioners
Cooling: Coolnet-supplied high-efficiency precision AC units optimize thermal management.
2. Power Distribution Room
UPS System: 4 × 250kVA modular UPS units , each supported by:
2 battery banks (8 banks total).
Each bank: 40 × 12V/70AH lead-acid batteries (320 batteries total).
Power Distribution: Multiple switchgear cabinets for redundant power routing.
Project Summary:
Coolnet delivered an integrated, turnkey solution featuring:
✅ Scalable Architecture: Modular design allows rapid capacity expansion.
✅ Energy Optimization: Precision cooling and high-efficiency UPS reduce PUE to ≤1.3.
✅ Resilience: N+1 redundancy for power/cooling ensures 99.99% uptime.
✅ Sustainability: Heat containment and efficient component design minimize carbon footprint.
This facility sets a benchmark for next-gen data centers in the Asia-Pacific region, combining Coolnet’s innovation with Singapore’s vision for a digital-forward economy.