Project overview
Coolnet worked with a local network and IT solutions provider to deliver a university data center in Egypt. High ambient temperatures and future campus IT expansion shaped the enclosed, dual-row design.
Project configuration
- IT racks
- 8 racks, configured at 5 kW per rack
- Cooling
- 4 × 25 kW in-row units with R134a
- UPS
- 2 × 40 kVA rack-mounted modular systems
- Battery configuration
- Designed for 30 minutes of backup
Monitoring tailored to the operator
The DCIM system includes energy-consumption analysis and visibility into power usage and environmental conditions.
Design through commissioning
Coolnet supported configuration design, optimization, installation and commissioning guidance with the local IT provider. High-temperature cooling was selected around the site conditions.