Project overview
Tau Cloud converted an existing car-wash and flower-shop building into a server-room facility in Astana. Coolnet coordinated the modular infrastructure with the requirements of the adapted building.
Project configuration
- IT racks
- 40 across 3 modules
- Total IT load
- 536 kW
- Precision cooling
- 18 units
- Power
- 2 UPS systems with batteries and distribution
Design, manufacture and support
Coolnet developed the configuration, manufactured and delivered the equipment, then sent engineers to provide startup, commissioning and operating guidance at the site.
Site conversion
The project adapts an existing commercial building for server-room leasing and sales. Its electrical, cooling and monitoring infrastructure is coordinated across three modular systems.